Getting Real With Machine Control
by Joseph V.R. Paiva PLS, PE, PhD
October 1, 2004

Bob
Parker (center) of Laser Specialists Inc. of Olathe, Kansas, explains some of
the many benefits of Leica Geosystems’ GradeStar 3D automatic machine control
system to Dave and Steve Newton of Cutting Edge Excavating, Louisburg, Kansas.
(Or how do I get started, and who can help me?)
The
use of sophisticated, modern measuring tools such as Real-Time Kinematic (RTK)
Global Positioning System (GPS) and robotic total stations has radically
changed the operational and financial picture of construction surveying. In
recent years the technology behind these tools has been transferred to
construction machines--including bulldozers, graders, excavators and
scrapers--and has provided great efficiencies for the firms using them. When
GPS and robotic technologies are coupled with other sensors that tell the
machine’s control display unit where the cutting edge is with respect to the
existing and design surfaces, the operator is able to work more efficiently to
convert the designer’s work into reality. With this advanced technology now
installed on heavy equipment, it is even possible for these machine control
systems to perform the grade adjustments within the final few tenths of a foot
automatically by controlling the machine’s blade or bucket
directly.
But, getting to this “real world of machine control” requires dedicated effort.
Interested firm managers must ask vendors tough questions and do rigorous
financial and operational analyses before deciding on and implementing such
systems. What are some of these steps? Let’s take a look at some of the
implementation challenges facing acquirers of these new technologies, and
consider how to successfully tackle these issues.
The Four Aspects of Machine Control

Seiler
Instrument's Stephen Koehler, PLS, trains Mike Hampel of Fred Weber Inc. on the
Trimble Advanced Tracking Sensor robotic instrument, part of the Trimble
BladePro3D machine control system, for Fred Weber Inc.’s Cat 14H Global motor
grader (shown in background). The Trimble ATS is the sensor to control the
elevation of the blade of the motor grader to .02 feet.
Tom
Seiler, GPS marketing manager for Seiler Instrument and Manufacturing Co. of
St. Louis, says that there are four main aspects a contractor should
investigate when considering to implement machine control: the survey aspect,
the machine aspect, the data prep aspect, and the installation and training
aspect. “When we go over these [aspects] with the contractors, they readily
understand what the issues are, even if they don’t know exactly how to tackle
them,” Seiler says. As with many new technologies, the buyer, who is the
contractor, often doesn’t know what challenges he will face. Time after time,
contractors who have successfully installed and operated machine control
systems for their earthmovers will say that having a dealer who understands the
challenges, and more importantly has, in partnership with the contractor, the
means to deal with them successfully, is the key to a machine control success
story.
The Survey Side

Stephen
Koehler, PLS, and Rob Swoboda of Seiler Instrument train Chris Wilmes, senior
project manager and Mike Hampel, grade checker, both of Fred Weber Inc. on the
Trimble Site Control System 900. Behind them stands a Cat D6N Track-type
tractor running with a Trimble SiteVision system.
For
machine control to operate successfully, the surveying infrastructure needs to
be rock-solid. Without the usual frequency of visual guides such as stakes,
laths, ribbons and markers, a machine operating on the undifferentiated
landscape can wreak havoc if a strong network of surveying control doesn’t exist.
Reliable surveying control is necessary at the site to ensure that the “digital
staking” is properly set and immovable. Having surveyors, whether in-house or
subcontracted, who understand the needs of machine control is important.
Machine control just does not tolerate piecemeal coordinate systems or, as is
sometimes the case, no coordinate system at all. The consultant’s
responsibilities include understanding the datum and the coordinate system to
be used project-wide. This involves sound management and a project control
focus on the part of the surveyor, who must consult with the designers and
project managers to ensure that all are indeed “on the same page.”
The control must also be properly set and coordinated, and both the surveyor
and contractor must know that machine control is being used on the site versus
conventional tools. On sites where machine control is applied, there is a need
to place the control systems out of harm’s way. But equally important is
setting control that is accessible to dozers and graders. Without such
machine-accessible control, it is not possible to check the calibration and
accuracy of the machines, which in effect have become giant surveying machines,
or at least extensions of a huge, integrated surveying system.
For those instances where control on the site exists from different sources,
the surveyor’s job includes coordinating them all into one system and
publishing the coordinate values in all three axes. This should be done
regardless of whether the machine control is done in 2D or 3D, or with RTK GPS
or robotic total stations (or both). If one coordinate system is established,
then there will be no ambiguity or uncertainty about the values to be used for
machine check stations, instrument and backsight setup points, or bench marks
and reference points used to check the quality assurance of the surveying
systems.
The Machine Side

Rick
Jones, superintendent with Northwest Excavation of Rogers, Ark., verifies a
manhole cover elevation using a Topcon HiPer+ rover and Pocket 3D software
provided by Ozark Laser and Shoring of Springfield, Mo. Ozark recommended a
consultant to Northwest to perform surface file preparation. CAD files are E-mailed to the consultant who sends back
surface files to load to a flash card placed in the equipment.
Of
course, the contractor supplies the machines: the bulldozers, graders,
excavators and scrapers. To make these machines “machine-control capable,” the
contractor must rely on the dealer and the manufacturer that the dealer
represents to make sure the complete--and appropriate--kits are ordered for the
tasks at hand. Contractors should be aware that much variation occurs from year
to year in the details of a machine such as a bulldozer, and even from model to
model. Thus, it isn’t enough for a contractor to tell a vendor “I’ve got a D-6”
when ordering components for the machine. Using in-house experts who know the
intricacies of these machines is one of the many ways machine control dealers
must “equip” themselves to be sure they properly provide service to their
clients. Masts, cables, hydraulic valves, radio modems, displays and computers,
antennas and prisms, GPS receivers… this is where the majority of the money is
spent to equip the construction machine.
It is also now possible to equip some of the machines with automatic controls,
so that instead of providing a guide on where the cutting or biting edge must
be, the system itself controls it. When equipped with automatic controls, the
machine still requires an operator, partly for safety reasons, but even more
importantly because on early passes, the machine doesn’t “know” that
positioning the blade for all of the four feet of cut is not the way to get the
earth moved. Once most of the material has been moved out of the way, the
automatic system works wonderfully and consistently to grade the last few
tenths of a foot.
Contractors must plan for machine downtime from one to two days, depending on
whether they are equipping their machines for 2D or 3D work, and depending on
the complexity and size of the machine itself. When automatic control is
required, the job takes longer--often two to three days--since the hydraulic
system must be modified. Generally, this time includes installation of all the
system components as well as testing of the newly configured machine. Dealers
typically send out crews to do the installation at the contractor’s machine
yard, or as is frequently done, at the contractor’s jobsite. Often, additional
labor is required just to situate parts into place, and the machine operator or
mechanics provide technical input to make sure the installation is properly
done. In some cases, the dealer contracts with third parties to do the
installation.
When it is the contractor’s first
experience with setting up total stations or GPS base stations, the dealer will
often spend additional time with the contractor to instruct the contractor’s
crews on how to perform these vital setup tasks, or to provide background
information to the contractor’s project managers to ensure they can monitor the
work done by surveying consultants and be able evaluate their effectiveness.
“Generally, we find that contractors understand the problems of installing
hardware on the machine that is welded or bolted to it, or where we have to
tinker with the hydraulics,” says Greg Fearon, vice president and general sales
manager of FLT Geosystems, a surveying instrument dealer in Ft. Lauderdale,
Florida. “The hardest part is working with their personnel on the math and
surveying aspects--and that is where if they don’t have those skills
internally, a surveying consultant can be a good partner for machine control
implementation.”
The Data Preparation Side

Mark
Summerfield, Seiler Instrument’s 3D machine control installation and technical
support manager stands in the cab of a Cat 14H Global motor grader helping
train operator Earl Walker of Fred Weber Inc. on the operation of the color
display box of a Trimble BladePro3D system.
The
aspect of data preparation is the quietest and least visible of the phases of
making machine control come to life. Because data preparation is often
overlooked, it can be the most troublesome for the contractor. Understanding
the issues and making sure that qualified data prep experts are handling this,
whether at the contractor’s office, the designer’s office, the consulting
surveyor’s office or in the dealer’s office, will make the difference between a
smooth transition to machine control and a long--and often prolonged--expensive
mess. “Learning about the data prep process is a little bit of a surprise [for
most contractors],” says Randy Stewart, branch manager and 3D machine control
sales manager of Pacific Survey Supply in Wilsonville, Oregon. Here again, the
contractor is dependent on the dealer to provide guidance on how to manage the
data prep side of the machine control equation. The ideal situation occurs when
the designer knows that machine control will be used on the site and
understands exactly how plans and data are to be prepared to create the digital
data to be used by the construction machines. However, the key to successful
machine control, according to Stewart, is proper data preparation by machine
control-qualified consultants.
At least during the first few projects (and as-needed thereafter) when
implementing machine control, a qualified and reliable team is essential--one
that can analyze the design plans (whether on paper or digital) and assess the
work needed to be done to transfer the designs to the machines. It is a good
idea for this same team to then perform the data prep work. Sometimes,
especially if the job is small, the dealer can provide this support. A few
dealers even provide this service as an ongoing business. Most dealers know of
consultants who truly understand the intricacies of data preparation for
machine control. They can recommend a list of such consultants to the
contractor, and at that point it is up to the contractor to hire the
appropriate one. In many cases, these consultants may have worked hand-in-glove
with the dealer on early projects of another contractor, or the consultant may
have sent a team to be trained by the manufacturer (most can provide
documentation, short courses or consultants to help their surveyors learn this
new aspect of managing and quality controlling geodata). Dealers often
recommend self-taught consultants who have achieved good results from working
with other contractors to provide data prep services.
A contractor must know that even when plans have been digitally prepared, they
may not be machine control-ready. To make the plans complete and ready, the
designer of the data must have specifically understood that digital files
customized for the contractor’s machines were also to be prepared. If the
designer does not know this, then seldom will the paper and digital documents
be complete without the assistance of a geodata prep team to bring that data
into machine control readiness.
For machine control to be fully effective, the digital files on each
construction machine must have data that is specifically geared to that
machine. This includes a digital terrain model (DTM) file representing the
finish surface (for that machine) to provide guidance to the operator on the
cut or fill required, based on the position and elevation of the current
position of the blade. It generally also shows enough surface details (such as
existing fences, roads, designed lot lines or pavement or shoulder edges) on
the operator’s display for the operator to “get the picture” of what he or she
is attempting to build.
The Installation and Training Side
Most
of the installation and training issues of machine control have been covered in
the previous sections. However, two key points remain to be discussed. One
important part of the installation step of machine control involves the
creation of a digital file of the machine’s measurements that are installed in
the machine’s registry. This is the machine-specific calibration that relates
the horizontal and vertical offsets of the prism or GPS antenna (or points when
it is a dual GPS antenna system) to the edge of the blade.
Another important aspect to machine control is operator training. This is
usually done immediately after installation, if the machine is onsite or if
there is a test site near the machine yard. Typically, this can take anywhere
from a couple of hours to a couple of days depending on the situation. When the
machines (operator-trainees) are relatively close to each other onsite, the
dealer’s trainer can train several at the same time. Many times, the initial
reaction of operators to the implementation of machine control has been
resistance. But after a short time working with the new system, quite often
only a day, the resistance diminishes or disappears entirely. One of the most
important parts of operator training is teaching them to check in regularly at
the control installed by the surveyor and to evaluate whether the machine is
still in calibration. This calibration check is often done by locating a corner
of the blade over a stake and measuring its distance above the stake,
calculating that elevation and comparing it with the value on the machine’s
display. “When we do training, we often work with a machine control ‘champion’
within the contractor’s organization,” Pacific Survey Supply’s Stewart claims.
“The champion is involved in observing all aspects of the training of others
and the installation of the system. They observe the data prep process. This
gives them the ability to be the in-house support for the machine control
system.”
The Inside Details on Geodata Preparation
Very
often a consultant will use a CAD expert who is intimately familiar with
surveying, as well as a surveyor to get the data from design drawings converted
and prepped for loading into a machine. The consultant’s work will also include
any work necessary to get the system up and running, including verifying
control, making sure the published coordinate values are in the right system,
adding control and check points for the construction machines and the people
doing quality control, setting up the base station if GPS is being used, and
collecting any supplementary surveying data that may be required to make the
data onboard the machine as complete as possible. Other work that may be
required of the consultant includes being on-call to handle problems and
performing quality assurance. Services such as staking for curb and gutter or
utilities like sewers may also be provided by the consultant on certain
jobs--the concept of “stakeless grading” hasn’t done away completely with red
and blue tops.
“It doesn’t matter whether the plans are produced on paper or digitally,” says
Mark Mosby, CAD manager at Cole & Associates Inc. in St. Louis, a customer
of Seiler Instrument. “For us to successfully transfer the information to the
dozer or grader, we have to examine every piece of the design, especially when
it is assumed that the contractor can build it by going from template to
template. Depending on the complexity of the project, we sometimes have to
construct our own cross-sections and generate profiles at key points using the
existing and design surfaces at 5-meter intervals on straight portions and as
small as 1-meter intervals on curves to make sure there are no
problems.”
The consultant’s CAD expert needs to transfer the horizontal alignment,
vertical profile and typical cross sections into the machine so there will be
no gaps or “holes” when the system determines its position and tries to
determine grade at that location. Every template must transition smoothly to
the next, and there can be no ambiguity. Discontinuities can make the system
inaccurate, unreliable or incorrect. Thus, the CAD expert may have to tweak the
details provided by the designer to make sure that continuity exists between
cross sections, especially if the work being done is a complex site grading
operation or a complex road project. Particular care needs to be given to
checking the data for smoothness around ditches, transitions, superelevation
and widening.
The Benefits of Early Implementation
“When
it’s all done properly, it is very gratifying to hear the stories from the
contractors,” says Cole’s Survey Manager Terry Westerman. “[Recently], Seiler
installed a system on a grader, taking one morning to do it. The DTM prepared
by Cole was put on the machine. By the end of that same day, this newly
equipped grader had been used to lay down and grade the base rock for 1,600
feet of a two-lane road. By the end of the following day the asphalt paving was
complete.”
Fred Weber Inc. of Maryland Heights, Mo., was contracted for a project recently
for the Missouri Department of Transportation (DOT). This project was the first
time Fred Weber had used machine control. Instead of holding up progress while
the machine control was being prepped, Fred Weber asked Cole & Associates
to get started the conventional way, later transitioning to machine control.
“The idea was that the contractor could start the earthmoving, and once machine
control was ready to go they would have a graded surface to compare with, and a
way to compare productivity as well [between conventional staked grading and
stakeless grading]. The conventional/digital approach really worked for them,”
Westerman says. Where the two surfaces prepared by conventional and digital
methods came together, the difference was indistinguishable. “The contractor
was impressed that when we had their operators drive up to a check stake, the
vertical difference missed by less than the width of a little
finger.”
The crowning touch in the Missouri DOT project was when the contractor was able
to use the DTM prepared for the graders and bulldozers in the GPS equipment
used to do quality assurance. Handheld GPS rovers and vehicle-mounted units
were used for this purpose. The quality checking proved near perfection. With a
well-prepared digital model, the machines were able to get the grading done
with no mistakes. The common problems of mistaking the notation on a stake and
cutting where fill was required just did not happen. A key element of
successful integration of machine control, says Westerman, is that “the radical
difference in technology means that you have to have an open mind about the process
you invent--you have to let the technology lead you.” Even as a consultant to
the contractor, this new form of surveying services has required a radical
change at Cole & Associates--in the number of personnel in a crew
(reduced), the number of crews (increased) and the technical skill and
knowledge of the crew (much increased).
With this system, it has been no problem to handle changed conditions onsite,
according to Cole’s Mosby. “A telephone conduit was found during excavation
that nobody knew about before the work started,” Mosby explains. “We sent out a
crew, surveyed it, sent the information to the designers, evaluated and prepped
the data from the new design, and a new card was ready for the earthmovers in
under a week.”
Bruce Flora, owner of Flora Surveying Associates in Glens, Va., has been
working on machine control projects along the eastern seaboard for four years.
His advice to contractors: “Don’t assume electronic files from designers are
correct until you or someone you trust has checked them. You never know what
you will get. Making sure you can get the cooperation of the engineers is
important, but sometimes it can be difficult. But above all, work on building a
relationship with a long-standing, qualified dealer with good support
capabilities. Don’t go for the cheapest; look at service, inventory and
troubleshooting capabilities. Ask questions about what they will do for you if
a system goes down.”
“When we sell machine control, we aren’t selling a product so to speak: it is a
process,” Stewart says. “So selling involves training the customer in the
process. Because changes occur periodically, it is important that the
contractor plans for periodic updates and re-training as well.”
Applying All Four Sides of Machine Control
Contractors
involved in grading sites and building roads are implementing machine control
with great enthusiasm. Because it is a newer construction process, a little
investigation of the technology, the manufacturer, the dealer and sources of
technical assistance to implement the system will have a huge payoff in both
the short and the long term. Some contractors have progressed sufficiently and
have a decided competitive edge. As Flora remarks: “The technology is here.
Stand on the wayside and watch it go by you. Get onboard before you have to
play catch up. Jump onboard but have a plan for what you will do next.”
Joseph V.R. Paiva PLS, PE, PhD
Joe
Paiva is a professional surveyor and professional engineer, and has obtained
his doctorate in civil engineering. He is a published author, speaker and
consultant to developers and marketers of products for the positioning
industry.
Did you enjoy this article? Click
here to subscribe to the magazine.