Site Prep

GPS Boosts Road Builders’ Productivity

by Jeff Winke

October 6, 2010

  • ARTICLE TOOLS
  • shareShare
  • ReprintsReprints
  • PrintPrint
  • EmailEmail
Enlarge this picture

Bob Bergkamp Construction equips its dozer with Trimble GCS900 Grade Control Systems with dual GPS.

System turns skeptical construction workers into technology fans.

Though the city of McPherson lies just east of the center of Kansas, it is dead center of a major construction project.

In early summer 2009, officials announced the first road-building project in Kansas funded by the American Recovery and Reinvestment Act of 2009—the construction of a new 22-mile stretch of the K-61 Highway corridor, running diagonally from McPherson southwest to connect with Hutchinson, Kansas. The new $64 million road project stretches from McPherson County into Reno County.

The four-lane highway project is a new road alignment just west of the original two-lane K-61 Highway. One of the reasons for moving the road from its existing path is to locate it farther away from the railroad tracks in order to meet new environmental standards and to avoid disruption of the agriculture for the nearby ranchers. Sections of the project called for incorporating the footprint of the old road, but much of the planned construction required purchasing right-of-way rights from farms abutting the new highway.

Starting off with Software

Bob Bergkamp Construction of Wichita, Kan., won the bid for building an eight-and-a-half-mile section of the new K-61 Highway project.

The company used a 3D model of the project to support the GPS-enabled heavy equipment, total stations and data collectors used throughout the jobsite.

“We took the Kansas Department of Transportation’s CAD files and used Trimble Terramodel and Trimble Business Center-Heavy Construction Edition office software to convert the files for use on our machines and rovers,” says Justin Howard, field engineer with Bob Bergkamp Construction.

“The Trimble software gave us all the jobsite and surface modeling we needed to establish the road parameters.”

Clearing the necessary 200- to 400-foot wide swath for the new road was a challenge. “This was one of the bigger clearing jobs we’ve had to do on a highway project,” says Rick Thome, project engineer with Bob Bergkamp Construction.

“It took a month to cut through the brush, trees and heavily wooded land. We’d clear a section, start the actual road-building process and then move down onto a new section.”

After clearing the new roadway swath, the initial push was to establish the bridge berms so the two bridge contractors could complete the work. Overpass bridges required pilings be set anywhere from 60- to 200-feet deep, with footings at 8- to 10-feet. Bergkamp Construction needed to build 18 bridge berms that were about 20- to 25-feet above the road grade.

In its road building, Bergkamp Construction used an approximate 50/50 soil mix—which was about 1 million yards of on-site dirt and 1 million yards of imported dirt.

“We had to remove the top 6 inches and rework the bottom 6 inches, and then put that 6 inches back before the finish grading,” Howard says. “The dirt was tested to 90 percent density until we reached the top of the fill where it tested for 95 percent density.”

Grading with Precision

The Trimble systems put the site plan—design surfaces, grades and alignments—right inside the cab, helping the operator achieve a plus or minus one-tenth millimeter accuracy.

With an understanding that the road is only as good as the subgrade, Bob Bergkamp Construction knew that each lift required precision in the grade. The company used two motor graders and a dozer equipped with Trimble GCS900 Grade Control Systems with dual GPS. The Trimble systems put the site plan—design surfaces, grades and alignments—right inside the cab and helped the operator achieve the plus or minus one-tenth millimeter accuracy that Bergkamp Construction established as their standard.

“The blades have the Trimble MS990 Smart GPS Antenna, which is an integrated GPS antenna and receiver, and we have the most advanced control box available, the Trimble CB430 Control Box, with its very readable screen, even in bright daylight,” Howard says. “We have the technology to reliably achieve grade in one pass.”

For their stretch of the K-61 Highway corridor project, Bergkamp Construction used three Trimble SPS851 Modular GPS Receivers for semipermanent base station setups to support the grade checking, site measurement and stakeout. The combination radio and GPS receivers were set up on both ends and in the middle to ensure adequate coverage of the entire site.

“There’s a configuration function in the SPS851 that allows for multiple base points to run off the same continuous calibration,” Howard says. “This saved me at least a couple of days of setup time since each base station didn’t require the time to establish its location base point.”

Going the Distance

For Bob Bergkamp Construction, the eight-and-a-half mile K-61 Highway project was one of its longest distance road building projects. At their busiest, they had four crews amounting to about 30 workers at the site.

It was also the most GPS-based technology they’ve had on one jobsite. “Having the Trimble technology was a tremendous help, and it saved us time and increased production,” Howard says.

The company’s foreman was able to walk ahead of the production crew and establish points using the rover.

“This is far better than having to pull 100 feet of tape up a hill to stake it, and then run back down the hill to use an eye level,” Howard says. “Here in Kansas, a light breeze is 20 miles per hour, so that tape would be blowing around.

 “The technology helps cut production time,” Howard continues. “Most of the time you don’t need stakes.  The GPS-guided machine will do it for you. We can control the volume of fill with each lift by doing a vertical offset. It has really helped us maintain proper compaction, especially when we needed to transition Type A compaction to the Type AA. The inspectors are a lot tougher on the Type AA, which is that 18-inch zone at the top.”

Unusually wet weather created schedule challenges, but Bob Bergkamp Construction was able to complete the project on time. The project also had a bit of a learning curve for Bergkamp’s workers, who were initially resistant to using GPS grade control systems.

“Some of our employees were pretty old-school,” Howard says.

“But now that they’ve experienced the Trimble technology, they are confirmed believers in using technology. It didn’t take them long to see that once we finish something with the GPS-guided machine, 99.9 percent of the time there is no rework, because when it’s done, it’s done accurately.”

Jeff Winke
Jeff Winke is an independent construction writer based in Milwaukee. He can be reached through www.jeffwinke.com.

|PrintEmail

Comments (0) Post a Comment

No HTML or BBCode in comments please.



Did you enjoy this article? Click here to subscribe to the magazine.







A BNP Media Website