When Thompson Pump Company was contracted to dewater three acres of land in South Carolina in late 2006, it expected to complete the task in three stages. But as the project neared completion, Thompson’s team ran into an unexpected obstacle below the surface and had to add another stage to its pumping process.
Confronting the Conditions
 |
| At the project’s completion, 195 million gallons had been pumped through 3,150 feet of wellpoint system and 3,600 feet of discharge pipe.
|
|
Phillips & Jordan had initially planned for Thompson to complete a three-stage project at a target depth of 47 feet. Stage three started successfully with two 350-foot-long, 6-inch systems, again utilizing two Thompson 12-inch rotary pumps. Despite the fact that the pumps were placed at a depth of 36 feet and discharging through 500 feet of Thompson galvanized pipe, they quickly reached the original target depth of 47 feet. But, at 44 feet, an unexpected challenge was met: A very soft, impermeable layer of clay 5 feet thick was shelving water past the wellpoints and making the banks of the final cut unstable.
Thompson used a multi-pronged approach to find a successful cure for this situation. “First, we put shallow points in to catch water running across the clay layer,” Polzin explains. “Then we used sand wicks to puncture the clay layer and allow water to drain through.” Finally, the Thompson team installed a rocked French drain around the grade perimeter of the final slope. “We dug a ditch along the edge of the wall, filled it with rock along the edge and then put a pump at the lowest part. Whatever water makes it past the clay layer then falls into the rock.” A Thompson 4-inch vacuum-assisted pump and one backup pump kept the French drain sumped out at its lowest point.
Because the clay layer made the center of the excavation floor unstable and unsuitable for building, a fourth stage wellpoint system was installed to solidify the excavation floor. Using one Thompson 12-inch rotary pump to pump against 50 feet of static discharge head and 540 feet of discharge piping, stage four had the area dewatered and ready for building within a week.
After the area was cleared to 52 feet below natural ground elevation, a 2-foot layer of stone was poured across the entire excavation floor and a 1-foot mud mat was laid. Six weeks later, the stage four system was buried in concrete and the pump was removed. Twelve weeks after stage four was removed, the stage one pumps were pulled and removed.
In total, Thompson Pump’s team used 13 pumps and pumped an average of 1.3 million gallons of water a day. At the project’s completion, 195 million gallons had been pumped through 3,150 feet of wellpoint system and 3,600 feet of discharge pipe. The successful dewatering efforts made it possible for Phillips & Jordan to continue the project, knowing they could rest on a stable foundation.
Sidebar:
Company:
Thompson Pump Company
www.thompsonpumps.com Project:
Clear and dewater 52 feet below natural ground elevation for plant foundation on 3-acre site.
Location:
Fairfax, South Carolina
Equipment Used:
• Caterpillar D9 dozer
• Thompson Pump 12-inch rotary pumps